Garden Waste Collection Suspended
Becasue of the Covid-19 epidemic Cheshire West & Chester Council have decided to suspend the Garden (Green) Bin collections until further notice. Household wste and recycling collections will continue as normal. Full details can be found in The Parish Council/Public Notices on this website.
Covid-19: Village Support
A new page has been added to the website to provide help and assistance to villagers during these difficult times:
Covid-19: Village Support
We will keep this updated as the circumstances change.
Update on new Water Main on Huxley Lane
Work is progressing down Huxley Lane with the installation of a new water main, albeit slower than was originally envisaged. The current plan is that work will cease on 20th December for Christmas and New Year. When work recommences on the 6th January Huxley Lane will be closed from the A49 up to Rose Cottage for 2 weeks. The full water main installation is due to be completed by mid February.
As part of this process a considerable amount of damage has been done to the grass verges and Smithy Green in particular, but we have been assured by United Utilities that they will make good the damage caused by themselves, but probably not until the spring when grass starts to grow again.
New Water Main on Huxley Lane
The work on the replacement water main on Huxley Lane is progressing, but due to adverse weather conditions and some unexpected issues it is likely to take longer than 8 weeks. Rather than being completed by the end of November as originally hoped, the work is likely to continue to the 17th January. Work will cease on the 20th December and start up again in the New Year.
Unfortunately it will be necessary to close the road completely as the work moves closer to the A49, as the two-way traffic light system being used further away will not leave enough room for larger vehicles to pass through.
You will also have noticed that Smithy Green has been badly damaged by contractor vehicles. We are assured by United Utilities that this will be put right once the work is complete.